Manufacturing planning

Use Manufacturing to check which components, work center time and estimated costs are needed for a production plan. The page currently plans capacity. It does not reserve components, issue stock, record actual labor or scrap, receive finished goods, or post to accounting.

Plan five units

  1. Create a work center with its recurring weekly capacity in minutes.
  2. Save a BOM revision with a finished product, components per unit, component lead times and routing operations. Enter setup minutes, minutes per unit and the estimated cost per hour for each operation.
  3. Select that BOM revision, the material location and a quantity of five. Choose start and due dates within the same calendar week.
  4. Select Check materials, capacity and cost. Inspect component shortages and already planned work center time. Follow the source links to inspect the underlying records.
  5. Select Confirm capacity plan after checking the preview. The application checks current capacity again before saving. A shortage of material is retained visibly in the plan; planning capacity does not promise that stock is reserved.

Understand the estimate

Material cost is an estimate from current weighted average valuation at the selected location. A component without valuation makes the total unknown. Labor uses the routing rate, including setup time. Estimates currently require a default currency with two decimal places.

Capacity repeats weekly. Holidays, shifts, partial-week availability and other calendars are not inferred. Component lead time is shown for missing components and does not guarantee a delivery date.

Revisions, retries and cancellation

A saved BOM revision cannot be edited. Create a new revision for an engineering change. Existing plans retain their original cost and capacity snapshot.

Repeating the same confirmation after a failed response retrieves the existing plan. It does not reserve capacity twice. Changing the request starts a new confirmation. Cancel plan releases that plan's capacity; repeated cancellation has no additional effect. Neither planning nor cancellation changes inventory or accounting balances.

Permissions

Inventory read permission is required to inspect the page. Inventory management permission is required to create BOMs, work centers and plans or cancel a plan. Every source record must belong to the active tenant.

Quantities are whole base product units. Fractional quantities and unit conversions are not supported. Only stock without a variant is included. Components are flat product lines: nested BOM expansion and multilevel cycle analysis are not implemented. Self-consumption and duplicate component lines are rejected. Material availability does not deduct other plans and does not reserve stock, so multiple plans can project against the same on-hand units.

BOM revisions are immutable in the database. A product cannot have two revisions starting on the same date. Select the newest revision effective on the plan start date; the following revision ends the previous effective interval. Existing snapshots and retries remain unchanged after a new revision. Retrying a cancelled plan returns that cancelled plan and never reopens it.

Release an order and issue components

Select Release on a planned order to reserve every BOM component at its location. Release is all or nothing: if one component has too little available stock, nothing is reserved and the order stays planned. A released order keeps its work center capacity. Cancelling a released order returns the reservation.

Open the plan and use Component issue to issue reserved units to the order. Enter the units and select Issue. Stock and the cost layers of the issued units are consumed, and the order shows the issued units and the material cost. An issue can never exceed the open reservation, and repeating the same command has no further effect. An order with issued components or reported progress cannot be cancelled. Finished-goods receipt and accounting postings are not available yet.